Project Inquiries Are Up. Signed Design Work Is Still Down.

AIA reports rising project inquiries alongside declining signed design contracts. Learn how to plan A&E capacity around committed work and delivery stage.

Key takeaways

  • AIA reported that September inquiries rose modestly while signed design contract value continued to decline.
  • A November AIA white paper found the ABI relationship with construction spending had weakened and its lead time had lengthened.
  • Keep inquiries, proposals, signed work, and active production in separate capacity-planning views.

Inquiries and signed work can move in opposite directions

AIA's September 2026 Architecture Billings Index score was 44.7, down from 47.2 in August. In its detailed September update, AIA also reported that project inquiries increased modestly while the value of newly signed design contracts declined further. These are survey index readings, rather than percentage changes in project volume.

That split matters when a firm decides whether to hire, subcontract, or rearrange production. An inquiry is a reason to pay attention. A signed, authorized scope with a start date is a stronger basis for assigning hours. Treating both as equivalent workload can pull capacity decisions too early or too late.

Keep the pipeline in separate stages

Keep a separate planning view for each stage. Update the project record when its authorization or start conditions change.

StageWhat it establishesStaffing use
InquiryEarly interestTrack potential demand and timing
ProposalPotential scope, fee, and scheduleModel a separate workload scenario
Signed agreementContracted scope, subject to start conditionsPut authorized work in the base plan once start conditions are understood
Active productionCurrent deliverables and deadlinesAssign hours by discipline and milestone

Confirm authorization and start conditions before allocating production hours.

Check the market forecast against project start dates

AIA's November white paper on the ABI and construction spending describes a slightly weaker correlation and a longer lead time. The relationship concerns architecture billings and later construction spending. It cannot provide a staffing schedule for an individual prospect.

The monthly indicators do not establish when a particular inquiry will become a signed project. A delay in one large project can also leave teams waiting even when the rest of the pipeline looks busy. Treat an index as context for a scenario, then check it against your own signed work, start dates, backlog mix, and project decisions.

Forecast workload by phase and discipline

Months of backlog compress several kinds of work into one number. A project in early design development and a project approaching a drawing issue can carry similar remaining duration while demanding very different production hours this week. A firm with the same headline backlog as another practice may need a different mix of architectural, structural, MEP, or BIM coordination support.

For each contracted project, check the authorized scope, milestone dates, current phase, staffing assumptions, and decisions still owed by the client or consultants. Put proposals and inquiries into separate scenarios with their likely start ranges. Then compare each scenario with available hours by discipline. This exposes a narrow production peak that a top-line backlog figure can hide.

Set a staffing trigger before the next surge

At a weekly staffing review, ask what work is authorized, which dates are firm, and which production tasks will exceed the team's available hours. Decide what evidence would move a proposal into the base plan. If a project slips, identify which people or deliverables can move with it.

Permanent hiring makes sense when demand is sustained and the work mix supports it. A bounded peak may call for temporary production capacity when the task, standards, and reviewer are clear. In either case, tie the decision to workload that can be scheduled. At the next staffing review, identify the authorized projects and milestones that would trigger additional capacity.