BuildTech Insights

LOD 300 vs. LOD 400: What A&E Buyers Should Specify

Understand LOD 300 and LOD 400 model-element requirements and define project milestones, uses, responsibilities, and information needs.

Introduction

When a project requests LOD 300 or LOD 400, the important question is what a particular model element must support, at which milestone, and who is responsible for it. The BIMForum describes LOD as Level of Development and distinguishes it from the amount of visual detail alone. A model can contain elements at different levels. BIMForum 2025 LOD Specification, Part I

What LOD 300 means

LOD 300 elements are represented so that their quantity, size, shape, location and orientation can be measured. That representation may support agreed design and coordination uses. It does not by itself mean that all elements are fabrication-ready, or that the entire model is suitable for every downstream use. Requirements should be defined for the relevant elements and project milestone.

What LOD 400 means

LOD 400 describes elements represented with detail sufficient for fabrication, assembly and installation. BIMForum relates this to shop-drawing-level development and notes that most models have few, if any, LOD 400 elements. A requirement for an entire model to reach this level can therefore be substantially broader than a project needs.

LOD 400 is not merely a prettier LOD 300 model. It supports a different intended use for specified elements. The project team should define the scope, inputs, review and responsibility for those elements.

Define information beyond geometry

The LOD label alone does not specify every non-geometric property a project might need. If equipment identifiers, materials, performance data or asset information are required, list those fields separately with their format, responsible author and delivery milestone. Align the requirements with the project BIM execution plan and agreed information exchanges. NIBS: Project BIM Execution Planning

Write a useful requirement

Specify which elements require each LOD, the intended model use, the project milestone, the author and reviewer, and the non-geometric information to be delivered. Name the LOD reference and edition. The AIA describes a model element table as a way to define element authorship and development levels at project milestones. AIA: G201 and G202 FAQ

A well-defined requirement enables buyers to request the right model elements and information rather than relying on a single label for the entire project.